Performance of Super-Large-Span Tunnel Portal Excavated by Upper Bench CD Method Based on Field Monitoring and Numerical Modeling

Table 1

The support system of the tunnel portal.

Temporary supportφ50 × 5 pregrouting pipe: first row L = 6 m, angle = 6°; second row L = 3m, angle = 15°; circumferential spacing = 40 cm, longitudinal spacing = 1.2 m.

Primary supportC25 shotcrete, thickness = 30 cm; φ25 hollow grouting anchor L = 500 cm, spacing = 60 cm; double layer φ8 steel mesh, spacing = 20 × 20 cm; H200 steel rib, spacing = 60 cm; reserved deformation = 20 cm.

Secondary liningC30 concrete, thickness = 70 cm; 40 g/m2 nonwoven fabrics; EVA waterproof cloth, thickness = 1.5 mm.