Construction Time of Three Wall Types Made of Locally Sourced Materials: A Comparative Study
Table 12
Time necessary to prepare the clay for compaction.
| Clay preparation difficulty | Clay placement for mixing | Transport of admixtures | Processing with milling machine | Pouring into moulds | Total time |
| Medium-cohesion 801–1400 g/5 cm2 | m-h/m3 | 0.51 | 0.52 | 0.08 | 0.35 | 1.46 |
|
|
Source: own study.
|