Construction Time of Three Wall Types Made of Locally Sourced Materials: A Comparative Study

Table 14

Various works.

Various worksUnit of measureQuantity

Placement of levelling layer under ceiling beams for load-bearing outside walls plus extra for more difficult formwork and compactionm-h/m1.00
Placement of levelling layer under ceiling beams for load-bearing inside walls plus extra for more difficult formwork and compactionm-h/m2.00
Placement of window templates, removal completion of works, plus extra for more difficult formwork and compaction
Window templates above 0.5 m2m-h/pc0.55
Window templates below 0.5 m2m-h/pc0.40
Door templates above 0.5 m2m-h/pc0.55

Source: own study.