Research Article
Construction Time of Three Wall Types Made of Locally Sourced Materials: A Comparative Study
| Various works | Unit of measure | Quantity |
| Placement of levelling layer under ceiling beams for load-bearing outside walls plus extra for more difficult formwork and compaction | m-h/m | 1.00 | Placement of levelling layer under ceiling beams for load-bearing inside walls plus extra for more difficult formwork and compaction | m-h/m | 2.00 | Placement of window templates, removal completion of works, plus extra for more difficult formwork and compaction | | | Window templates above 0.5 m2 | m-h/pc | 0.55 | Window templates below 0.5 m2 | m-h/pc | 0.40 | Door templates above 0.5 m2 | m-h/pc | 0.55 |
|
|
Source: own study.
|