Time needed to build 1 m2 of the straw-bale clay wall.
| Operation | Standard time | m-h/m2 | % |
| Making inside clay plasters | 0.904 | 10 | Erecting wooden framework structure | 7.437 | 79 | Insulation of straw bales and fibreboard cladding | 0.366 | 4 | Making outside lime plasters | 0.640 | 7 | Total | 9.347 | 100 |
|
|