Time needed to build 1 m2 of the straw-bale clay wall.

OperationStandard time
m-h/m2%

Making inside clay plasters0.90410
Erecting wooden framework structure7.43779
Insulation of straw bales and fibreboard cladding0.3664
Making outside lime plasters0.6407
Total9.347100