Research Article
Study on Deformation and Stability of Rock-Like Materials Retaining Structure during Collaborative Construction of Super-Adjacent Underground Project
Table 3
Material parameters of rock-like material retaining structure.
| Project | Material of retaining structure | Material of the first inner support |
| K0+600-K1+074 section of Gongchang Road Project | Drilled grouting pile | Underwater concrete (C30) | Shrinkage compensating concrete (C30) | Pressure jet grouting pile | Ordinary portland cement (level P42.5) |
| Sun Yat-Sen University Station | Diaphragm wall | Underwater concrete (C35) | Concrete (C30) |
|
|