Research Article
Research on Dynamic Response of Shallow Buried Tunnel Lining Constructed by Drilling and Blasting Method
Table 4
Comparison of simulated and measured values of peak particle velocity (with in situ stress).
| Point | R/m | X velocity (cm/s) | Error /% | Y velocity (cm/s) | Error /% | Z velocity (cm/s) | Error /% | Resultant velocity (cm/s) | Error /% | M | S | M | S | M | S | M | S |
| 1# | 15 | 19.75 | 21.37 | 7.56 | 22.54 | 19.82 | 13.68 | 8.59 | 7.89 | 9.27 | 26.18 | 22.99 | 13.87 | 2# | 20 | 15.90 | 17.42 | 8.69 | 24.61 | 27.74 | 11.25 | 7.35 | 7.75 | 5.2 | 29.31 | 27.87 | 5.18 | 3# | 25 | 8.16 | 7.36 | 10.79 | 7.06 | 6.41 | 10.18 | 8.24 | 8.04 | 2.38 | 10.24 | 9.27 | 10.44 | 4# | 30 | 9.58 | 8.97 | 6.88 | 14.44 | 15.60 | 7.48 | 10.60 | 10.99 | 3.52 | 18.31 | 17.29 | 5.92 | 5# | 35 | 13.12 | 14.97 | 12.30 | 16.76 | 18.23 | 8.05 | 11.77 | 12.44 | 5.39 | 23.33 | 21.26 | 9.73 |
|
|
Note: R is the distance from the measurement point to the tunnel surface, M is the measured value, and S is the simulation value.
|