Research Article
Resource Constrained Project Scheduling Subject to Due Dates: Preemption Permitted with Penalty
Table 3
Computational results of the LINGO and SA.
| Number of activities | Number of resource types | Number of problems |
LINGO |
SA | NPO | ACNT-LINGO | NPM | ARD | ACNT-SA |
| 20 | 1 | 10 | 10 | 0.064 | 100 | 0.00% | 0.108 | 20 | 2 | 10 | 10 | 0.132 | 100 | 0.00% | 0.117 | 20 | 3 | 10 | 10 | 0.383 | 100 | 0.00% | 0.141 | 30 | 1 | 10 | 10 | 3.212 | 100 | 0.00% | 0.173 | 30 | 2 | 10 | 10 | 29.407 | 94 | 0.29% | 0.211 | 30 | 3 | 10 | 10 | 80.545 | 91 | 0.38% | 0.295 | 40 | 1 | 10 | 7 | 123.110 | 100 | 0.00% | 0.386 | 40 | 2 | 10 | 6 | 200.154 | 92 | 0.46% | 0.438 | 40 | 3 | 10 | 6 | 309.494 | 78 | 0.67% | 0.516 | 60 | 1 | 10 | 0 | — | 92 | 0.59% | 1.073 | 60 | 2 | 10 | 0 | — | 85 | 0.61% | 1.332 | 60 | 3 | 10 | 0 | — | 72 | 0.64% | 1.768 | 90 | 1 | 10 | 0 | — | 91 | 0.60% | 3.650 | 90 | 2 | 10 | 0 | — | 86 | 0.79% | 3.782 | 90 | 3 | 10 | 0 | — | 77 | 0.86% | 4.254 |
|
|