Research Article

Reinforcement Effects of Isolation Piles on the Adjacent Existing Tunnel in Building Construction

Table 5

Procedures of the model test.

Procedure numberProcedure instructions

1Initial state (construction of the diaphragm wall, isolation piles, anchor cable, and shield tunnel and reading initial values)
2Soil excavation to −133 mm depth
3Construction of sloping and the first-layer anchor cable
4Soil excavation to −266 mm depth
5Soil excavation to −400 mm depth
6Construction of the second-layer anchor cable
7Soil excavation to −533 mm depth
8Soil excavation to −667 mm depth
9Construction of the third-layer anchor cable
10Soil excavation to −800 mm depth
11Soil excavation to −933 mm depth
12Soil excavation to −1000 mm depth
13Waiting for 24 h after completion of excavation
14Loading foundation slab and weights of 1.2 kN
15Loading weights of 2.4 kN
16Loading weights of 3.6 kN
17Loading weights of 4.8 kN
18Loading weights of 6.0 kN
19Loading weights of 7.2 kN
20Loading weights of 8.4 kN