Review Article

Foam Concrete: A State-of-the-Art and State-of-the-Practice Review

Table 9

Application examples of selective fill with FC.

ReferenceTunnel nameCountryYearApplicationBrief descriptions

[235]Kent Thameside tunnelsUK2010ReclamationThe 50 m deep tunnel extends about 90 m, and FC with density of 400 kg/m3 and compressive strength of 0.5 MPa was backfilled.
[236]Dakota ProjectUSA2000Reinforcement backfillThe original granular backfill above the tunnel resulted in foundation foot settlement and finally caused structure deformation. The original filling was removed and replaced by 500 kg/m3 FC.
[237]FarnworthUK2015Auxiliary constructionThe 7800 m3 FC of 1100 kg/m3 and 1 MPa was used to backfill the one of a 300 m long double-hole tunnel so as to accept the Tunnelling Boring Machine (TBM).
[235]ThackleyUK2013Structural reinforcementAs more distortion was recorded, with the crown being forced upwards into a void. A total 2540 m3 FC with 1120–1130 kg/m3 and 1 MPa was required for fillers.
[238]HuashiyaChina2015Cavity fillingCavities and cracks appeared in secondary liner of tunnel, and then these defects were filled by FC grouting.
[235]Gerrards Cross projectUK2009Load reductionTo reduce dead load, pile walls were installed on both sides of the tunnel, and 26,000 m3 FC with 375 kg/m3 was used to form horizontal ground at the top of vault.
[239]WulaofengChina2009Seepage water treatmentThe seepage of tunnel side wall was serious, and some locations were even gushing, so FC was used as waterproof material.