The original granular backfill above the tunnel resulted in foundation foot settlement and finally caused structure deformation. The original filling was removed and replaced by 500 kg/m3 FC.
The 7800 m3 FC of 1100 kg/m3 and 1 MPa was used to backfill the one of a 300 m long double-hole tunnel so as to accept the Tunnelling Boring Machine (TBM).
As more distortion was recorded, with the crown being forced upwards into a void. A total 2540 m3 FC with 1120–1130 kg/m3 and 1 MPa was required for fillers.
To reduce dead load, pile walls were installed on both sides of the tunnel, and 26,000 m3 FC with 375 kg/m3 was used to form horizontal ground at the top of vault.